Tools2 work started 22-12-23

Work on the construction of Tools2 started in November and December 2023. First, the site was leveled and 2,000 tons of excess soil was removed. The trenches were then dug for waste water sewer, rainwater drainage, electricity, fiber optic and water pipes. Despite the wet weather, everything was ready so that Enexis could install the necessary low-voltage cables in the 3rd week of December, so that we can connect the units immediately in 2024 when the building is ready. Because the sewer and rainwater drains are deeper, this was done first, which also applies to the water pipes. The fiber optic supplier immediately laid a sleeve in which the fiber optic can be installed in the future without having to open the paving. The beginning has arrived!